Avenue Bellevue tops out – February 2023 construction update
Avenue Bellevue, the twin tower, 382-unit condo mega project that broke ground in 2019 announced this week that they’ve topped out both tours and are on track to complete the building this year. The Residences will complete in Q3 with the Estates following in Q4.
They also shared the following updates on each tower:
- Residences:
- Windows are in
- Crane removal early March
- Framing up to floor 21
- Flooring up to level 5
- Cabinets up to level 4
- Estates
- Windows will be done by end of February
- Crane removal early April
- Framing up to floor 19
- Flooring up to level 6
- Cabinets level 5